# PG&E Planning to Start Preliminary Potter Valley Project Decommissioning Work in Late November
- URL: https://www.mendolocal.news/pg-e-planning-to-start-preliminary-potter-valley-project-decommissioning-work-in-late-november/
- Published: 2026-11-16T17:01:37.000Z
- Updated: 2026-11-16T17:01:37.000Z
- Description: PG&E spokesperson Paul Moreno said crews expect to drill the first two of seven planned test borings at Cape Horn Dam in late November or early December.
- Author: Elise Cox
- Tags: Potter Valley, News

PG&E spokesperson Paul Moreno said crews expect to drill the first two of seven planned test borings at Cape Horn Dam in late November or early December, weather permitting — about five days of work, with the other five borings, underwater, following in summer 2027\. 

The borings will inform the design of a cofferdam and bypass channel that would let the utility wall off the dam's wet face, pump out the water, and route the Eel River around the work while crews take the century-old dam apart. 

"We build a cofferdam, a wall that is up against the wet side of the dam, and then you remove the water from there so you can work on the dam face," Moreno said.

The drilling is one of the first physical steps toward Pacific Gas and Electric Co.'s plan to tear Cape Horn Dam down — and it comes as the utility and the state remain at odds over how much water PG&E must release before the project winds down. Federal regulators gave the company conditional permission to bore the test holes in late October, as reported by [The Mendocino Voice](https://mendovoice.com/2026/11/pge-gets-conditional-ok-to-drill-into-mendocino-countys-cape-horn-dam/?ref=mendolocal.news). Days later, California's water regulators told those same officials that the utility still has not filed a water-quality certification they say its separate plan to cut Eel and Russian river flows requires.

On Oct. 29, the San Francisco dam-safety office of the Federal Energy Regulatory Commission (FERC) wrote to PG&E authorizing it to proceed with a drilling program at Cape Horn Dam, provided the company resolved four technical comments within 10 days. The comments, signed by Regional Engineer Frank L. Blackett, flagged two borings planned close to a concrete retaining wall and asked how PG&E would monitor the wall for "formation of new cracks" during drilling. They also questioned why two holes were planned at about 30 feet deep when the plan anticipated 20 to 60 feet of sediment. 

In a Nov. 5 response, PG&E's deputy chief dam safety engineer, Robert O. Ellis, said the comments had been "satisfactorily addressed" and submitted a revised plan. The utility filed within the 10-day window FERC's authorization required, clearing the way for the drilling to proceed. The drilling plan itself is withheld from the public record as critical energy infrastructure information.

PG&E's own Preliminary Engineering Report describes the role of the cofferdams. Crews would first build a small cofferdam along the river's right bank to wall off the dam's earthen embankment, then cut and armor a channel through that embankment to carry Eel River flows downstream while they work. They would install channel-spanning cofferdams upstream and downstream of Cape Horn Dam to seal off the work area, then drain the isolated stretch with pumps and siphons, passing the nuisance water downstream or into the diversion tunnel. The borings are meant to pin down sediment thickness and depth to bedrock, cofferdam height, seepage control, channel configuration, required excavation depth, and temporary slopes and erosion protection. Across the two seasons, Moreno said, the drilling adds up to about 15 days of work.

The drilling also needed California's sign-off, which came on a separate regulatory path. On Nov. 2, the California Department of Water Resources' Division of Safety of Dams — which regulates Cape Horn Dam under its state name, Van Arsdale Dam (No. 97-102) — filed a notice of exemption treating the "geotechnical exploration within the footprint of the dam" as categorically exempt from environmental review under the California Environmental Quality Act. 

The water-quality question is older and unresolved. On Nov. 6, the State Water Resources Control Board told FERC that PG&E's proposed license amendment, which would rewrite the project's minimum instream flows, still needs a Clean Water Act Section 401 water quality certification. The board asked FERC to order PG&E to file a new certification application. The board has pressed the point repeatedly. PG&E applied for a certification in February 2025, the board issued a draft that December, and PG&E withdrew its application shortly afterward, saying the draft did not reflect its planned revisions. The board's position is that PG&E's proposed flow reductions would increase the frequency and volume of spills at Scott Dam — a potential increase in discharge that triggers state review.

PG&E disputes that it needs a certification. In its September filing, the utility told FERC it does not intend to apply for a Section 401 certification, arguing that reducing the flows would not increase the existing discharge or add any substance to it, and so is not the kind of activity that triggers the requirement. It pointed to a federal appeals court ruling that a decrease in the water passing through a dam is not a "discharge" under the Clean Water Act.

The proposed amendment would replace fixed flow requirements with a "drought working group" process and manage releases to the East Branch Russian River between 5 and 25 cubic feet per second from mid-April through September, dropping to 5 cfs after Oct. 1 until Lake Pillsbury storage exceeds 36,000 acre-feet. It would set the Eel River below Scott Dam at 20 cfs year-round — the level for a critically dry year — and would remain in place until the project license is surrendered.

PG&E describes the changes as dam-safety measures. The utility notified FERC in March 2023 of potential seismic instability at Scott Dam and proposed keeping the dam's radial spillway gates open indefinitely to hold Lake Pillsbury at a lower level. It wants the reduced flows to stay in place until the license is surrendered and the dams are removed.

Both filings sit inside PG&E's larger plan to surrender its federal license and remove Scott and Cape Horn dams, keeping only the parts of Cape Horn needed for a proposed New Eel-Russian Facility — a new diversion meant to preserve water deliveries to the Russian River watershed and to the Potter Valley Irrigation District. That removal plan, negotiated locally among the Round Valley Indian Tribes, Sonoma Water, the Mendocino County Inland Water and Power Commission, California Trout, and Trout Unlimited, has drawn national opposition over the past year from U.S. Agriculture Secretary Brooke Rollins and the Elsinore Valley Municipal Water District in Southern California. FERC is still reviewing the surrender and decommissioning application.

Cape Horn Dam is also getting more immediate attention. Separately from the drilling, PG&E filed a work plan Oct. 6 to repair a void that had been observed near the toe of the dam's embankment. In an Oct. 13 letter, FERC Regional Engineer Frank L. Blackett authorized the utility to begin the repair on receipt of the letter, provided it addressed four comments — among them a drawing of the void collapse and a clearer temporary emergency action plan — within 10 days, and set a Feb. 28, 2027 deadline for a report documenting the finished work. PG&E answered the comments Oct. 22, within the window, telling FERC they had been "satisfactorily addressed." A copy of FERC's letter went to the state Division of Safety of Dams.

### You Read Our Stories. Please Help Fund Our Newsroom.