# Noyo Harbor's Sea Wall Buckles as the Storm Season Opens
- URL: https://www.mendolocal.news/noyo-harbors-sea-wall-buckles-as-the-storm-season-opens/
- Published: 2026-11-17T18:37:53.000Z
- Updated: 2026-11-17T18:39:11.000Z
- Description: A weekend storm damaged the sea wall that keeps river mud out of the Noyo Harbor marina in Fort Bragg. Harbormaster Anna Neumann estimates the emergency repair at $400,000 and says it can't wait.
- Author: Elise Cox
- Tags: Fort Bragg, News

FORT BRAGG, Calif. — A weekend storm damaged a sea wall at Noyo Harbor, and Harbormaster Anna Neumann says it needs to be repaired right away to keep river mud from filling the marina.

The sea wall is a line of sheet piles that blocks mud from the Noyo River from entering the marina basin. A west swell struck the harbor's west-facing jetty entrance over the weekend, and the plastic sheet piles are snapping, Neumann said during a walking tour of the damage. If more break loose, she said, they could damage the aging wooden docks behind them, let mud into the marina, and could expose damage that is now hidden.

"We should repair it tomorrow," Neumann said. "Or as soon as possible."

Neumann estimated the emergency repair at about $400,000\. She said she would rebuild the wall with sheet-metal piles instead of the plastic ones.

Neumann said Noyo is one of the last publicly managed marinas on the North Coast still using original wooden docks, and that Humboldt, Crescent City, and Bodega Bay have switched to concrete. A full replacement would cost $30 million to $40 million, she said.

The weekend tide ran high. Neumann said the gauge read 9.5 feet, compared with a usual high tide of about 7 feet, and that she nearly lost the roughly five feet of free board clearance on the dock pile — the point at which a dock can float free of its piling.

A second barrier is also failing, Neumann said. An earthen wall around an 11-acre sediment-containment site the district leases from the city is sloughing into the water under the same swells, which she said could wash river mud onto the beach. The U.S. Army Corps of Engineers is scheduled to repair the harbor jetty and dredge the federal channel next fall.

Neumann said she emailed Rep. Jared Huffman's staff the morning after the storm to describe the damage and ask whether the congressman could help secure a disaster declaration that would open access to FEMA funding. Huffman's office, responding on background, said the congressman and his staff are "in frequent contact with the harbor master and fully support her work to improve aging and damaged infrastructure at Noyo Harbor," and that meeting FEMA's thresholds is "always a challenge" but that they "will do whatever we can to help the harbor district respond to storm damage from this event and more."

Mendocino County 4th District Supervisor Bernie Norvell, whose district includes the harbor, expressed his support for Neumann.

Neumann said the sea wall will stay as it is until it can be repaired. More storms are in the forecast.

### You Read Our Stories. Please Help Fund Our Newsroom.

MendoLocal.News was created by locals for locals. We pay attention and dig deeper and we distribute for free. With your support, we can keep going.

3× Give today and donors will triple your gift. 

[Fund Our Newsroom](https://www.mendolocal.news/donate/)